Tuesday, May 8, 2012

Some Finish Work Has Begun!



 My kitchen ceiling!


 Daddy's Little Helper

 Fire Place is in!
 Kitchen is ready for cabinets!

 Too cute not to share!
 Master Bedroom
 Finally have stair treads!
 Picking out stone for the fireplace!
 Flooring upstairs
And....my cabinets are in!

Saturday, March 31, 2012

The downstairs

These pictures are from my phone, but my baby is asleep on my lap so this is the best I could do.
This is my stamping/scrapbooking room that just got drywalled yesterday.
My kiddos sitting in the window.
Here is a view into our living room from the kitchen.
The dining room from the living room.
The kitchen
The living room again.

Tuesday, December 6, 2011

Finally an Update!

Kitchen
Kitchen from living room
View from the kitchen into the living room
Tray ceiling in our bedroom/dining room
The arch above our shower
Our whirlpool tub!

Where the kitchen table will set

Another view from the loft
The living room from the hallway

Ava's closet (she chose this room because it had a bigger closet than Emelia!)
Ava's Room
Kid's bathroom (soon to be decorated in owls!)
Emelia's room
Emelia's window seat
Our half sided house!
Kale's room
The landing, a place for the kid's toys!
The dining room
Looking into the kitchen from the living room, love the 3 arched doorways!
The dining room view from our living room
The kids in their Christmas pjs!
The house is coming along. Drywall is almost finished upstairs and should be ready to paint this week! The downstairs is next and should start hanging sometime next week. Dave is about to wrap up all the loose end electrical items. The porch is ready to be built and the rest of the siding is waiting to go up! Lot's of stuff to keep Dave busy this winter!

Sunday, September 18, 2011

An Update....Finally

It's been hard to keep this updated with everything going on, Ethan's Rodeo, our new baby, Emelia, the house building.....etc! Here are some outside and inside shots of our progress. The plumbers have finished the rough-ins, the HVAC are finishing up our geothermal system rough-in, Dave has started on the electric wiring, siding is up on the East and partially on the North side of the house, the garage is up, all the stud walls are up, the cabinets are ordered, plumbing fixtures and lighting fixtures have been picked out and the tile/flooring is all picked out too. We are hoping to start drywall in the next couple weeks and to get the house sealed up before winter hits again. Dave thinks we could be in before the end of winter.....but winter technically goes until sometime in March!


Looking up from our great room....kind of hard to visualize, but the room on the left is the dining room.



The siding on the east side of the house.



A view from the winery road.




Another view from the winery road.

The kids shower/tub upstairs.

A look over our great room from the upstairs hallway




Our steps up to our landing.

Thursday, June 23, 2011

We have a Roof and Windows!

We are "still" working on our house, the weather just hasn't been cooperating the way we would like. The roof was finally finished the last couple weeks in May. Then we started to get more rain and couldn't get the JLG around to close up the peaks of the house. So this is how the house sat for quite a while. Didn't they do a nice job with the backfilling! We don't have those big mounds of dirt anymore so I can actually see the house from my kitchen window!Here is a shot of the house with all of the windows (minus the front door)! You can click on the picture to see them in more detail, but I believe this is what they refer to as prairie style windows. Now I can't wait to see what the house will look like with our wrap around porch.Here is a view of the East side of the house!And the back side!And this is where the garage will eventually be!The back of the house!

This is a view from the inside of the house looking down onto our living oom!










Another shot of our open living room1